(Summary description)The Z-shaped hoist is a device that integrates conveying and lifting. The device adopts a segmented connection type and has a more flexible layout. Because it can be lifted and conveyed, it saves space for some manufacturers who are lifting up. This equipment It adopts chain conveying, which is relatively stable, not only does not cause materials to fall from the hopper, but also the equipment is relatively stable during operation, with relatively low noise, easy to disassemble and easy to repair, and is an ideal conveying device. It is currently widely used in all walks of life. People are using it.

What are the precautions for Z-shaped hoist test machine

(Summary description)The Z-shaped hoist is a device that integrates conveying and lifting. The device adopts a segmented connection type and has a more flexible layout. Because it can be lifted and conveyed, it saves space for some manufacturers who are lifting up. This equipment It adopts chain conveying, which is relatively stable, not only does not cause materials to fall from the hopper, but also the equipment is relatively stable during operation, with relatively low noise, easy to disassemble and easy to repair, and is an ideal conveying device. It is currently widely used in all walks of life. People are using it.

  • Categories:Industry trends
  • Author:
  • Origin:
  • Time of issue:2020-09-30
  • Views:0
Information

   The Z-shaped hoist is a device that integrates conveying and lifting. The device adopts a segmented connection type and has a more flexible layout. Because it can be lifted and conveyed, it saves space for some manufacturers who are lifting up. This equipment It adopts chain conveying, which is relatively stable, not only does not cause materials to fall from the hopper, but also the equipment is relatively stable during operation, with relatively low noise, easy to disassemble and easy to repair, and is an ideal conveying device. It is currently widely used in all walks of life. People are using it.

   After purchasing the Z-shaped hoist, do not come up and start using it after the installation is complete. You must start the test machine first. Today I will introduce you to the precautions for the test machine.

   1. Check whether the installation is correct. First, check whether the equipment is installed. Check if there are no screws on the cabinet, make sure that each screw has been tightened. If any missing screws are found, they need to be repaired in time to avoid some failures caused by loose screws. It is the injury of personnel. Secondly, check whether the hopper and the material strip are installed normally. If it is abnormal, it will cause problems. Install and check in strict accordance with the requirements, and pay attention to the precautions.

   2. The machine is fixed. First of all, ensure that the bolts are installed properly and that the machine is fixed. Normally, the lower level needs to be fixed by bolts. If the lower level is longer, you can fix more bolts. Some users place the lower level in the pit. At this time, fix the bolts. The effect is better. The vertical section can be fixed. Use some steel brackets to cooperate with the site and install it to a suitable position to ensure that the machine does not shake. The upper level is usually fixed with steel brackets, which can prevent the machine from shaking during operation.

   3. Start idling. The Z-shaped hoist is turned on and idling to check whether the equipment has abnormal noise. If there is abnormal noise, it needs to be shut down immediately for inspection. After the equipment is overhauled, start it again to avoid minor faults in the equipment. Then check the bearings, motors, and motors after there is no abnormal noise. Whether the temperature of the reducer is normal, it is required that the temperature rise is not more than 60 degrees after two hours of operation. Some users have forgotten to add lubricating oil before, causing the temperature of the reducer to be too high. In this case, just add it and check whether the lubrication seal Good, it requires more than two hours to run the machine idling.

   4. Trial production. Afterwards, trial production can be carried out, and the trial production can be fed. It is required to put a little less material at the beginning, and slowly start to put more materials. It is best to use a feeder to adjust the feeding speed of the feeder from small to large, and then slow Start production slowly. It should be noted that violent feeding is prohibited, and uniform feeding is required.

 

Keyword:

Scan the QR code to read on your phone

HOT LINE: 

Contact: Manager Pang
Phone:
+86-13932836877, +86-15832856785,

+86-13315840327
Tel: +86-318-4869777
Fax: +86-318-4868277
E-mail: 384023722@qq.com
Add: West Of Nanxiao Road, Matou Town,

Hengshui City, Hebei Province, China

MOBILE SITE

Copyright © 2020 Hengshui Chang Hong Mining Machinery Co., Ltd.  All Right Reserved  冀ICP备13014199号-1